New Pigging facilities in Nowra (NSW) and Canberra (ACT)

20 March 2015

 

 

It is with great satisfaction we can confirm the successful completion of all in-service welding at the Nowra and Canberra sites. Our Client Jemena/Zinfra have also successfully completed hot tapping/stoppling/re-commissioning work at four of the five sites, and expect the final Canberra site to be complete just prior to Easter. Overall mechanical completion will be achieved mid-April, with remaining civil work due to be complete on time (late April, 15).

 These have been complex brown field projects requiring large excavation around live gas mains, pipeline assessments, staged mechanical installations, in-service welding, by-pass operations, hot tap/stoppling and re-commissioning in tight timeframe to minimise interruptions to important gas networks.

 

Culcairn Compressor Station

We have also had crews involved in both above ground and underground piping hook ups for APA’s new Compressor at Culcairn. We have also assisted with some minor plant modifications at the Young Compressor Station. These works are nearing completion and our crews are looking for new opportunities in NSW, ACT and Queensland.